PUBLIC NOTICE: Sewer/Storm Water Project Schedule

Town of Mountain View Sewer and Storm Water Project Schedule

Updated 11-5-2019.

11/1/19 to 11/8/19: Alley work between Eaton and Fenton, just north of 41st

11/1/19 to 11/8/19: Paving, install storm inlet & grading – NE corner of 41st and Fenton

11/7/19 to 11/8/19: Paving work in alley between Ames and Benton and 41st and 43rd

11/6/19 to 11/8/19: Point repair work (and then paving) on sewer line between Benton and Chase and 41st and 43rd