PUBLIC NOTICES: Wastewater & 41st Ave/Storm Water Project Schedule

Town of Mountain View Wastewater and 41st Ave./Storm water Project Schedule

1-9 Through 1-18-2020

Finish Utility Work on Fenton St. N. of 41st Ave: Finalizing storm sewer inlet, pipe and manhole installation.

Concrete sidewalk corner work- Multiple corners on W.41st Ave. This corner work includes finishing corner drainage and installation of “truncated dome” ramp covers to help the visually impaired.

Paving of 41st Ave. corners and Fenton Street N. of 41st Ave (weather permitting).